22/01/2026
Construction Update | Living Choice Parkwood
We’re excited to share the latest progress on Stage 1.
The Lexington Building:
Podium: Final clean completed and services commissioned
Levels 1–3: Final clean completed and services commissioned
Levels 4–5: Final fitments and painting underway
Facade: Completed from Level 1 above
Balustrades: Completed from Level 1 above
Balcony tiling: Completed from Level 1 above
Render and paint: Completed from Level 1 above
Current works: Podium works, planters, concrete works and landscaping in progress
To learn more and to view our latest timelapse video, click below.
https://www.livingchoice.com.au/news/48130/