11/07/2025
Work continues to progress steadily on the East Lothian Crematorium project, being delivered by City Gate Construction.
This week saw continued stonework on the main entrance, further development of the chapel ceiling, and roofing works including tiling, leadwork, and flat roof membrane installation. Windows and glazing are being installed, plastering has begun in key internal areas, and work on the floral tribute walkway is well underway. The coffin store roof has now been completed, and boundary wall construction using reclaimed stone is progressing.
Looking ahead, next week will focus on completing the stone facade around the entrance, building the reception porch, advancing roofing and drainage work, and continuing with internal finishes. Equipment for the cremator room is due to arrive, and fencing work along the boundary lines will continue.
Thank you to everyone on-site for the continued hard work and dedication as we move closer to completion.