19/06/2025
Significant progress continues to be made on-site as we move through week 46 of the build with City Gate Construction Ltd. Recent achievements include:
- Stonework installation progressing well on the main entrance and across the west and east elevations
- Roof tiling works underway, with single ply membrane gutter flashing preparation ongoing
- Windows and glazing are being installed across the building
- Electrical containment is advancing throughout the chapel, staffroom, and reception areas
- Ceiling boarding is underway in the chapel, alongside decorative works to the cremator room ceiling and steelwork
- Work on pathways and gardens is ongoing, including compressed gravel paths and kerbing around car park areas
Looking ahead, focus will turn to completing stone facades on all elevations, continuing external landscaping, floor screeding inside the chapel and vestry, further rendering works, and installation of doors and internal wiring.
Thanks to all teams involved for their continued hard work and collaboration as the project moves steadily toward completion.