Work continues to progress well at our new site in Cramlington, Great North Crematorium, with strong developments now reached at the end of week 24.
Brickwork and blockwork are advancing steadily with the second lift now underway, while scaffolding has been lifted to allow roofing works to begin. External works are also moving forward at a good pace, helping to shape the overall look and feel of the site.
Across the grounds, bunds have been dressed in preparation for the Spring seeding plan, with topsoil now spread to support this next stage. Progress is also being made within the Memorial Garden, where border and stonework to the paths are taking shape.
Works to the lower level roof have now started, marking another key milestone in the build.
It is great to see continued progress across all areas of the site and I look forward to sharing further updates as the project develops.