Gud evening everyone! Here is the update on Astral Hub project located in Lipa Batangas as of March 30,2021
-Ongoing welding works on framework of gas canopy, target to finish all trusses by next week
- Ongoing drywall frames installation in apollo and disgnostic
- Exterior walls in Apollo already finished
- Electrcal works in Apollo ongoing
- Second floor slab at food hub already done tonight
- Half of Commercial Building already ready for roofing, trusses installed
- Next week to target remaining roofbeams and trusses
- Waiting for delivery of AAC blocks, Roofings, Gas Pipes, Fusion Machine, Rebars, other requests
- Please see photos below for your reference.