PAUNAWA
Ano: NGCP and PELCO II Scheduled Power Interruption
Kailan: Marso 12, 2025 (Miyerkules)
Oras: Pagitan ng 6:00 ng umaga hanggang 7:00 ng gabi (mga 13 na oras)
Mga Apektadong Lugar:
GUAGUA, SASMUAN, LUBAO:
Lahat ng Barangay
ILANG BAHAGI NG BACOLOR:
Lahat ng Barangay maliban sa Brgy. Maliwalu at Calibutbut
ILANG BAHAGI NG STA. RITA:
Brgy. San Vicente, San Jose, San Juan, San Isidro, San Basilio, Sta. Monica, San Agustin, San Matias at Becuran (maliban sa Razon hanggang Dila-Dila)
ILANG BAHAGI NG FLORIDABLANCA:
Brgy. Gutad at Anon (ilang bahagi)
Dahilan:
NGCP
• Reconductoring along Hermosa-Guagua 69kV Line from 336.4 MCM to 795 MCM; and
• TL Maintenance activities along the line
PELCO II
• Construction and rehabilitation of lines;
• Substation Works;
• Metering Works;
• O & M Works; and
• R. O. W. / Clearing of lines