02/01/2025
Dear Customer,
Please be advised that our clinic will be closed tomorrow January 03,2025 due to a scheduled power interruption in the area. We apologize for any inconvenience this may cause and appreciate your understanding. Should you have any urgent matters, please feel free to reach out.
Thank you for your cooperation!
Best regards,
Admin
PAUNAWA
Ano: NGCP at PELCO II Scheduled Power Interruption
Kailan: Enero 3, 2025 (Biyernes)
Oras: Pagitan ng 6:00 ng umaga hanggang 6:00 ng hapon (mga 12 na oras)
Mga Apektadong Lugar:
MABALACAT - Lahat ng Barangay
MAGALANG - Brgy. Sta. Lucia Barrio at Sta. Lucia Resettlement (Phase 1 at 2)
Dahilan:
NGCP
• Electrical testing of new 69kV power circuit breaker, disconnect switches and earthing switch;
• Commissioning and energization of new 69kV power circuit breaker, disconnect switches and earthing switch at Mexico Substation;
• Testing of feeder protection relays;
• SCADA control integrity test & alarm status validation test for the new power circuit breaker; and
• TL maintenance along the line.
PELCO II
• Payout of 795MCM ACSR segment of 69kV line in front of Mabiga Substation;
• Payout of 795MCM ACSR segment of 67kV line in front of Sta. Maria Substation;
• Resetting of primary protection of 10 MVA mobile substation;
• Replacement of 69k disconnect switch at Mabiga Substation;
• Substation works;
• Metering works;
• O & M works; and
• Clearing of lines
Para sa kaalaman ng lahat.