08/24/2025
Due to an electrical fire that happened on Friday, August 22nd, suites 7E/F, 7C/D, 7B and 7A of James Campbell Plaza are out of power.
Per the property manager:
“The first step is to remove all of the damaged electrical conduit, wire, and meter banks (this work started over the weekend) and next they are having to repair the section of block wall that was pulled away from the building so the electricians can re-attach their strutt to the wall which was also started over the weekend. The electricians will be back on Monday to reinstall strutt and conduit. Unfortunately the meter banks have a lead time of 3 to 5 business days so they will not be able to be installed until the latter part of next week. We hope to be energized by Aug 30, but it could roll into the following week before final inspections and energization occurs.”
This is definitely not the ideal start to the week, but we appreciate your patience while we get everyone rescheduled. While it’s an inconvenience, we’re grateful it wasn’t worse!!