01/23/2026
Last week’s “Scorpions On The Trail” Work Summaries
Tuesday January 20th – A small crew of 2 (Doug and Sig) returned to Clark Creek trail to try and complete construction on series of steps heading up a steep grade. It was a cold icy morning, but we were soon warming up as the sun burned off the fog. One step was already completed from the previous workday. All the cedar boards were previously cut with lap joints for assembly of the remaining steps. So, we made rapid progress and got the remaining 5 additional steps in.
Thursday January 22nd – A big crew of 13 arrived at Fall Creek on a very cold and foggy morning. A crew of 5 gathered the power tools needed to work on Puncheon construction on the Clark Creek trail. The rest of us followed them up the trail with 8 more 4x6x5ft cedar deck planks in hand that were needed to complete the puncheon decking.
After hauling the deck planks up 8 of us returned to the cars leaving the puncheon crew on their own. Our task was to log out the Dolly Varden section of the Fall Creek trail. The windstorm last month brought down quite a few more trees on this 3.4-mile section. We split into two groups of 4. On crew started at the Dolly Varden TH and worked their way up stream. The rest of us started where we parked and worked downstream. We were also planning to restore some sections of tread that needed work. Unfortunately, the ground was so frozen that tread work was quite difficult. But the log out went smoothly, about 20 logs were bucked and the crews met roughly in the middle of the trail. We will have to come back to complete the tread work when the ground thaws.
Meanwhile the puncheon crew enjoyed working in full sunshine. They had to cut and transport several more cedars to complete the stringers and have enough material for the bull rails. They got everything leveled and squared, the stringers pinned with rebar and the decking laid out to be sure there was enough. Next time they need to spike down the decking attach the bull rails and the project will be complete.
Hope to see you on the trail soon.
Next week's projects:
Thursday January 29th - Winberry Tie logout and brushing
Sign up link: https://bttr.im/pbhxz
Thursday February 5th - South Willamette Trail brushing and logout
Sign up link: https://bttr.im/ee7zv