09/28/2024
Great news for our clients who’ve been asking!
Progress on Veterans Drive!
Paving activities on the Veterans Drive Project are anticipated to begin on October 2, 2024 and is expected to be substantially completed by October 11, 2024, weather permitting!
Project activities include removing existing pavements, curbs, and sidewalks to install new pavement, water mains, and drainage improvements, along with curb adjustments to create traffic-calming bulb-outs. The project also involves installing new sidewalks, asphalt, and road striping for travel lanes and bike lanes.