RTE 85 in Waterford and Montville is getting milled and paved. You have likely seen work on the catch basins for several weeks, so we all knew it was coming. Here is the projected schedule, but we would recommend using others routes if possible for the duration of the project.
Route 85 construction/paving Route 85 from Cross Rd to Satchetello Dr. in Montville.
Anticipated:
Milling start date: July 8, 2024
Milling end date: July 19, 2024
Milling is planned for Monday thru Friday during the day from 0700 hours to 1700 hours. The milling will start from Montville and work south to Cross Road.
Anticipated night time paving
Paving start date: July 21, 2024
Paving end date: July 25, 2024
Paving will start from Cross Rd and move north to the area of Industrial Dr. in Waterford. Night time paving hours will be 1700 until 0500 hours, Sunday to Thursday
Daytime Paving
Paving start date: July 29, 2024
Paving end date: August 2, 2024
Daytime paving will start at Industrial Dr., moving north to Satchetello Dr in Montville. Monday to Friday 0700 hours to 1700 hours.